Editor: Liu Chang, Lu Hong
On March 27th, the Third Company of Sunsun Construction held a special meeting on construction schedule at the Dali Haidong New Town bridge and tunnel project department. Susun Construction CEO Zou Zhaoji, Chief Engineer Zhao Wenzheng, Chairman of the Third Company of Susun Construction Quan Guoshao, Vice Chairman Fu Min as well as department heads attended the meeting. In the meeting, construction schedule and managerial ideas on bridge and tunnel projects of the Third Company of Susun Construction were reported and discussed.
In the meeting, Fu Min reported the preparations of project department construction and supporting facilities on construction site. He also explained the detailed tasks for the next stage. Quan Guoshao highlighted the division of work concerning project implementation plan and time nodes.
Zhao Wenzheng suggested strengthening on standardization and normalization of on-site facility construction. Meanwhile, he indicated the seriousness of setting plans, objectives and time nodes and he also analyzed the possible difficulties and resistance.
In the end, Zou Zhaoji asked the team to implement the construction of supporting facilities at the project department as soon as possible, accelerate construction progress, and normalize overall image. He demanded all departments to strengthen mutual collaboration and cooperation, enhance team contribution, and improve overall working efficiency.
This meeting not only summed up the work accomplished of the Dali Haidong New Town bridge and tunnel project, but also provided a direction for the priorities for the next phase.